The Trail So Far:
Late in 2004, the Pleasant Hour Ladies Club and
several community members formalized ideas to attach indoor restrooms to
the existing hall. On
A 23’ X 54’ addition
that included a conference room, storage, men’s and women’s restrooms
and an extension for the kitchen was designed, with the help of Tim
Belton. Fundraising for the
$427,000 addition was immediately begun.
Sue Wallis spearheaded efforts to seek a
Late in 2006, the RCT was notified that the Wyoming Business
Council would award us a $300,000 CDBG grant.
The project was put out to bid, Bob Fulton and Back Again
Restoration was the only bid received.
We moved forward with the procedure to sign a contract.
In January of 2008 Bob Fulton informed us he was unable to get
bonding and was no longer interested in the project.
We did some calling and got some cost estimates that shocked us.
In the interim the costs had risen; a much needed new roof would
cost $200,000, the addition $333,000 and the wrap around deck $100,000.
This totaled $630,000, $200,000 more than we had funds available.
So the RCT went back to the drawing board and putting the project
out to bid with some major revisions.
In May of 2008, we signed a contract with Dale Buckingham
Architects LLC, to serve as architects and oversee contractors. We chose
Rosebud Log homes out of
In June of 2009, the existing metal roofing was removed and Y
Environmentals removed and disposed of the asbestos contaminated
materials. Rosebud Log Homes then placed a vapor barrier over the
remaining roof.
On
On
On
On
On
In June the Recluse Community Hall was decommissioned. Its 76
years of stalwart service lives on in the hearts and memories of its
people.
On July 22, 2010 the bid process was concluded by choosing SS
Construction of Gillette as our general contractor. July 29th,
we signed a design contract with SS for $16,000 and began the design and
permit phase again.
Our web hosting is complements of Visionary Communications Network. Thank You VCN.